After a very cold winter that put a halt on progress a lot of work continues on the new building.  The stucco on the old hall area is done and the front ramp is in the middle of being poured.  Next week a new sidewalk will be put in and stucco will begin on the new section of the building.  Contractors are working inside finishing electrical in the engine room, painters are beginning their work and floor finishes are going to start next week.  We are hoping to move in by mid April.  Thank you again for the continued support.